Home › Guides › G99 explained

G99 Explained: Grid Approval for Solar and Batteries

What G98 and G99 are, which one your system needs, and how long approval takes.

Updated 10 November 2026 · SolarGridVault

The short answer: if your solar and battery inverters add up to more than about 3.68kW on a normal single-phase home, your local electricity network operator has to approve the system before it's switched on. That's a G99 application. Your installer makes it for you, and it usually takes a few weeks.

What are G98 and G99?

They're rules from the Energy Networks Association for connecting anything that can send electricity into the grid, including solar panels and home batteries. Your local network operator (often called the DNO) uses them to make sure its cables and substations can cope. In Sheffield and the rest of Yorkshire, the network operator is Northern Powergrid.

G98G99
SizeUp to 16 amps per phase: about 3.68kW single-phase, 11.04kW three-phaseAnything larger
ProcessFit first, then notify the network operator within 28 daysApply first; connect only once approved
Typical waitNoneA few weeks, sometimes two to three months
Who does itYour installerYour installer

What counts towards the limit

Examples

SystemRouteWhy
3.6kW solar inverter on its ownG98Below 3.68kW
Any of our Home 5, Home 12 or Home 16 bundlesG99The 8kW hybrid inverter is above 3.68kW
Existing 3.6kW solar plus a separate 3.6kW battery inverterG99About 7.2kW in total
Three-phase home with a 10kW inverterG98Below 11.04kW on three-phase

There's also a quicker G99 "fast track" for some systems with inverters up to about 7.36kW and an export limit. Our 8kW inverter is just above that, so systems built around it go through the normal G99 process. Plan for that from the start.

How the G99 process works

  1. Your installer applies. They send the network operator the system design, a wiring diagram and the inverter's grid certificate. We give your installer the inverter documents they need.
  2. The network operator reviews it. It checks the local network can take the extra power. This usually takes a few weeks, longer in busy areas.
  3. You get a decision. Usually an approval, either as applied or with an export limit. Occasionally the operator asks for changes, or needs to do work on its own network first.
  4. Your system is fitted and switched on. The installer fits and commissions it, then confirms the details with the network operator.

Don't switch on before approval. A G99 system mustn't be connected to the grid until it's approved. Ask your installer to apply as soon as you've chosen a system, so the approval is ready when the equipment arrives.

What an export limit means

If the local network is busy, the operator may approve your system but cap how much power you send to the grid, for example 3.68kW. It doesn't limit how much solar you produce or store. The inverter and smart meter measure what's leaving your home and keep it under the cap automatically. With a battery you use most of your own solar anyway, so an export limit usually makes little difference to your savings. It can reduce export payments on very sunny days.

Common questions

Do I have to pay for a G99 application?

Ask your installer whether their price includes it. The network operator may charge if your connection needs work on its network, but it will tell you before anything goes ahead.

What if my application is refused?

Outright refusals are uncommon for home systems. More often the operator offers an export limit, which your system can work with.

Do I need the approval to get export payments?

Energy suppliers may ask for proof that your system is properly connected, along with your MCS certificate, before they pay you for exported electricity. Keep the paperwork your installer gives you.

G98, G99 and G100 are Energy Networks Association engineering recommendations for Great Britain. Your installer and network operator confirm exactly what applies to your property.

See the numbers for your home

Our free calculator uses your usage and tariff to recommend a battery and show the payback. Or ask us and we'll work it out with you.